MEMORANDUM FOR THE CHIEF OPERATING OFFICERS OF SELECTED DEPARTMENTS
AND AGENCIES
FROM: |
Ed
DeSeve /s/ |
|
|
SUBJECT: |
Progress
Addressing the Year 2000 Computer Problem in Mission Critical
Systems |
As noted in OMBs most recent report quarterly report to the
Congress, "Progress in Year 2000 Conversion", many agencies are
not demonstrating they are making adequate progress in addressing
the year 2000 problem in their mission critical systems. OMB is
concerned about the risk to the government of the failure of such
systems. Therefore, OMB will more closely monitor agencies
progress in fixing mission critical systems. To assist in that effort,
please provide, by June 26, a copy of your agencys plan for
monthly progress toward making its mission critical systems year
2000 compliant, including when systems being repaired are expected
to complete the renovation, validation, and implementation phases.
For Departments, please provide such a plan for the Department as
a whole and for each major component. Attachment A, is an example
of the summary information that we expect to derive from the plans
provided. Beginning August 10, and subsequently on the tenth day
of each month thereafter, please provide a report which shows the
actual progress made in the previous month relative to the plan.
Feel free to include explanatory information about the progress
reported. Please provide the plans to Ed Springer, Room 10236 NEOB,
Washington, D.C. 20503 (phone: 202 395-3562, fax: 202 395-5167).
He is also available to answer any questions. Thank you for your
continued hard work on this critical effort. Working together, I
am confident that we can minimize the impact of this problem. Selected
Departments and Agencies:
Agriculture
Commerce
Defense
Education
Energy
Health and Human Services
Housing and Urban Development
Interior
Justice
Labor
Transportation
Treasury
State
U.S. Agency of International Development
Office of Personnel Management
Attachment
A
Schedule
for Mission Critical Systems to be Compliant
Department/Agency
|
Number
of
Systems 1/
|
7/98
|
8/98
|
9/98
|
10/98
|
11/98
|
12/99
|
1/99
|
2/99
|
3/99
|
Departments
Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 2/
|
100
|
36
|
40
|
45
|
49
|
55
|
62
|
71
|
85
|
100
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component As Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 2/
|
32
|
12
|
13
|
15
|
19
|
25
|
31
|
32
|
32
|
32
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component Bs Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 2/
|
21
|
10
|
10
|
10
|
13
|
13
|
16
|
16
|
17
|
21
|
Actual
|
|
|
|
|
|
|
|
|
|
|
1/
The number of systems is total number of mission critical
systems minus those being retired.
2/
Also include previously reported estimates, if the current
estimates have changed.
|
Schedule
for Mission Critical Systems to be Renovated
Department/Agency
|
Number
of
Systems 3/
|
7/98
|
8/98
|
9/98
|
10/98
|
11/98
|
12/99
|
1/99
|
2/99
|
3/99
|
Departments
Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 4/
|
|
|
|
|
|
|
|
|
|
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component As Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 4/
|
|
|
|
|
|
|
|
|
|
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component Bs Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 4/
|
|
|
|
|
|
|
|
|
|
|
Actual
|
|
|
|
|
|
|
|
|
|
|
3/
The number of systems is the number of mission critical system
that are being or have been repaired.
4/
Also include previously reported estimates, if the current
estimates have changed.
|
Schedule
for Mission Critical Systems to be Validated
Department/Agency
|
Number
of
Systems 5/
|
7/98
|
8/98
|
9/98
|
10/98
|
11/98
|
12/98
|
1/98
|
Departments
Plan
|
|
|
|
|
|
|
|
|
Current
Estimate 6/
|
50
|
17
|
19
|
24
|
29
|
34
|
40
|
50
|
Actual
|
|
|
|
|
|
|
|
|
Major
Component As Plan
|
|
|
|
|
|
|
|
|
Current
Estimate 6/
|
18
|
8
|
8
|
9
|
11
|
12
|
15
|
18
|
Actual
|
|
|
|
|
|
|
|
|
Major
Component Bs Plan
|
|
|
|
|
|
|
|
|
Current
Estimate 6/
|
17
|
5
|
6
|
8
|
10
|
12
|
13
|
17
|
Actual |
|
|
|
|
|
|
|
|
5/
The number of systems is the number of mission critical system
that are being or have been repaired.
6/
Also include previously reported estimates, if the current
estimates have changed.
|
Schedule
for Mission Critical Systems to be Implemented
Department/Agency
|
Number
of
Systems 7/
|
7/98
|
8/98
|
9/98
|
10/98
|
11/98
|
12/99
|
1/99
|
2/99
|
3/99
|
Departments
Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 8/
|
50
|
7
|
9
|
12
|
16
|
20
|
26
|
34
|
41
|
50
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component As Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 8/
|
18
|
3
|
3
|
3
|
6
|
6
|
7
|
7
|
12
|
18
|
Actual
|
|
|
|
|
|
|
|
|
|
|
Major
Component Bs Plan
|
|
|
|
|
|
|
|
|
|
|
Current
Estimate 8/
|
17
|
2
|
2
|
4
|
5
|
6
|
8
|
11
|
12
|
17
|
Actual
|
|
|
|
|
|
|
|
|
|
|
7/
The number of systems is the number of mission critical system
that are being or have been repaired.
8/
Also include previously reported estimates, if the current
estimates have changed.
|
|