OMB COST ESTIMATE
FOR PAY-AS-YOU-GO CALCULATIONS
Report No: 551
Date: 01/12/01
- LAW NUMBER: P.L.106-577 (S. 2749)
- BILL TITLE: California Trail Interpretive
Act
- BILL PURPOSE: (1) Establishes the California Trail Interpretive Center near Elko,
Nevada; (2) Authorizes the conveyance of National Forest System lands to public school
districts for educational purposes; (3) Provides for a study of the Golden
Spike/Crossroads of the West Heritage Area Study near Ogden, Utah; and (4) Establishes
the West Historic District in Ogden, Utah.
- OMB ESTIMATE: P.L.106-577 authorizes
the acceptance of donations from the state of
Nevada, Elko County, and the city of Elko to build the proposed interpretive center. Cash
donations received can be spent without further appropriation. A lag is expected between
the receipt of the donations and the spending of the money.
|
(Fiscal years; in millions of
dollars) |
|
2000 |
2001 |
2002 |
2003 |
2004 |
2005 |
Net costs.................................... |
0 |
0 |
0 |
-3 |
3 |
0 |
- CBO ESTIMATE:
|
(Fiscal years; in millions of dollars) |
|
2000 |
2001 |
2002 |
2003 |
2004 |
2005 |
Net costs.................................... |
0 |
0 |
0 |
-3 |
3 |
0 |
- EXPLANATION OF DIFFERENCES BETWEEN OMB AND CBO ESTIMATES:
OMB and CBO have the same estimates.
- CUMULATIVE EFFECT OF DIRECT SPENDING AND REVENUE LEGISLATION
ENACTED TO DATE:
|
(Fiscal years; in millions of dollars) |
|
2000 |
2001 |
2002 |
2003 |
2004 |
2005 |
Outlay effect.............. |
34 |
7,887 |
12,198 |
14,554 |
15,750 |
16,863 |
Receipt effect............ |
-8 |
-2,558 |
-3,850 |
-3,906 |
-3,582 |
-3,806 |
Net costs.................... |
42 |
10,445 |
16,048 |
18,460 |
19,332 |
20,669 |
NOTE: Pursuant to P.L.106-554, the
pay-as-you-go balances that would result in a sequester for
FY 2001 will be set to zero in OMB's final sequestration report.
| |