Swan Lake/Lake Tyee Intertie

1 recipient will receive $3,200,000. This is a first-time earmark.
Year Enacted: 2005
Description: Construct the Swan Lake-Lake Tyee Intertie. The Intertie comprises a fifty-seven (57) mile 138kV (69kV initially) hydroelectric transmission line connecting the Four Dam Pool Power Agency-owned hydroelectric projects at Swan Lake on the Upper Carroll Inlet and Lake Tyee on the Bradfield Canal. Work to be completed under this grant is clearing of the final one mile of right-of-way, and construction of the tower foundations along the entire 57-mile route.
 
Beneficiary/Recipient Amount ($K) Program Type Address
The Four Dam Pool Power Agency (067113931) $3,200 Non-Profit
703 West Tudor Road, Suite 102
Anchorage, AK
Citation
Source: Appropriations Report Language - Conference
Reference: P.L. 108-447
Method: User entered excerpt
Citation Excerpt: ENERGY AND WATER APPROPRIATION For expenses of the Denali Commission including the purchase, construction and acquisition of plant and capital equipment as necessary and other expenses, $67,000,000 nothwithstanding the limitations contained in section 306(g) of the Denali Commission Act of 1998, $2,500,000, to remain available until expended: Provided, That of the amounts provided to the Denali Commission, ... $3,200,000 is for the Swan Lake/Tyee Intertie project;

Last Modified: 16-Apr-2007