May 21, 1993
TO THE HEADS OF EXECUTIVE DEPARTMENTS AND ESTABLISHMENTS
SUBJECT: Value Engineering
1. Purpose
2. Supersession Information
3. Authority
4. Background
5. Relationship to other management improvement processes
6. Definitions
7. Policy
8. Agency responsibilities
9. Reports to OMB
10. Inspectors General audits
11. Related Guidance
12. Effective date and Implementation
13. Sunset review
14. Inquiries
1. Purpose. This Circular requires Federal Departments and Agencies to use value engineering (VE) as a management tool, where appropriate, to reduce program and acquisition costs.
2. Supersession Information. This Circular supersedes and cancels OMB Circular No. A-131, Value Engineering, dated January 26, 1988.
3. Authority. This Circular is issued pursuant to 31 U.S.C. [[section]]1111.
4. Background. For the purposes of this Circular, value analysis, value management, and value control are considered synonymous with VE. VE is an effective technique for reducing costs, increasing productivity, and improving quality. It can be applied to hardware and software; development, production, and manufacturing; specifications, standards, contract requirements, and other acquisition program documentation; facilities design and construction. It may be successfully introduced at any point in the life-cycle of products, systems, or procedures. VE is a technique directed toward analyzing the functions of an item or process to determine "best value," or the best relationship between worth and cost. In other words, "best value" is represented by an item or process that consistently performs the required basic function and has the lowest total cost. In this context, the application of VE in facilities construction can yield a better value when construction is approached in a manner that incorporates environmentally-sound and energy-efficient practices and materials.
VE originated in the industrial community, and it has spread to the Federal Government due to its potential for yielding a large return on investment. VE has long been recognized as an effective technique to lower the Government's cost while maintaining necessary quality levels. Its most extensive use has been in Federal acquisition programs.
An August 1991 recent audit of VE in the Federal Government by the President's Council on Integrity and Efficiency concluded that more can and should be done by Federal agencies to realize the benefits of VE. Reports issued by the General Accounting Office and agency Inspectors General have also consistently concluded that greater use of this technique would result in additional savings to the Government.
5. Relationship to other management improvement processes. VE is a management tool that can be used alone or with other management techniques and methodologies to improve operations and reduce costs. For example, the total quality management process can include VE and other cost cutting-techniques, such as life-cycle costing, concurrent engineering, and design-to-cost, approaches, by using these techniques as analytical tools in process and product improvement.
VE contributes to the overall management objectives of streamlining operations, improving quality, reducing costs, and can result in the increased use of environmentally-sound and energy-efficient practices and materials. The complementary relationship between VE and other management techniques increases the likelihood that overall management objectives are achieved.
7. Policy. Federal agencies shall use VE as a management tool, where appropriate, to ensure realistic budgets, identify and remove nonessential capital and operating costs, and improve and maintain optimum quality of program and acquisition functions. Senior management will establish and maintain VE programs, procedures and processes to provide for the aggressive, systematic development and maintenance of the most effective, efficient, and economical and environmentally-sound arrangements for conducting the work of agencies, and to provide a sound basis for identifying and reporting accomplishments.
8. Agency responsibilities. To ensure that systemic VE improvements are achieved, agencies shall, at a minimum:
9. Reports to OMB. Each agency shall report the Fiscal Year results of using VE annually to OMB, except those agencies whose total budget is under $10 million or whose total procurement obligations do not exceed $10 million in a given fiscal year. The reports are due to OMB by December 31st of the calendar year, and should include the current name, address, and telephone number of the agency's VE manager.
The report format is provided in the Attachment.
Part I of the report asks for net life-cycle cost savings achieved through VE. In addition, it requires agencies to show the project/program dollar amount thresholds the agency has established for requiring the use of VE if greater than $1 million. If thresholds vary by category, show the thresholds for all categories. Savings resulting from VE proposals and VE change proposals should be included under the appropriate categories.
Part II asks for a description of the top 20 fiscal year VE projects (or all projects if there are fewer than 20). List the projects by title and show the net life-cycle cost savings and quality improvements achieved through application of VE.
Part III requires agencies to submit a detailed schedule of year-by-year cost savings, cost avoidances and cost sharing with contractors for each program/project for which the agency is reporting cost savings or cost avoidances. The aggregate total of all schedules shall equal the totals reported in Part I.A. of the annual report.
10. Inspectors General audits. Two years after the issuance of this revised Circular, Agency Heads shall ask the Inspectors General (IGs) to audit agency value engineering programs to (1) validate the accuracy of agency reported value engineering savings and (2) assess the adequacy of agency value engineering policies, procedures and implementation of this revised Circular. Periodically thereafter, agency IGs shall audit agency reported VE savings as the need arises.
11. Related Guidance. In general, value engineering investments should have positive net present value when discounted with the appropriate interest rate, as described in OMB Circular No. A-94, section 8.c. For detailed guidance on value engineering, refer to the appropriate sections of the Federal Acquisition Regulations.
12. Effective date and Implementation. This Circular takes effect within 30 days of its publication in the Federal Register. Heads of departments and agencies are responsible for taking all necessary actions to assure effective implementation of these policies, such as disseminating this Circular to appropriate program and other staff, developing implementation strategies and initiating staff training. Since these policies must be implemented in the Federal Acquisition Regulation (FAR), agencies should not duplicate the development of implementing procurement regulations being undertaken by the Federal Acquisition Regulatory Councils. However, implementation of these policies in the FAR must be accomplished within the time period specified below, with inclusion in agency solicitations and resulting contracts, as appropriate, to occur immediately thereafter.
Pursuant to subsections 6(a) of the Office of Federal Procurement Policy Act, as amended, (41 U.S.C. 401 et seq.), the Federal Acquisition Regulatory Councils shall ensure that the policies established herein are incorporated in the FAR within 180 days from the date this Circular is published in final form in the Federal Register. Promulgation of final FAR regulations within that 180 day period shall be considered issuance in a "timely manner" as prescribed in 41 USC 405(b)."
13. Sunset review. The policies contained in this Circular will be reviewed by OMB five years from the date of issuance.
14. Inquiries. Further information about this Circular may be obtained from the Office of Management and Budget (OMB), 725 17th Street, NW, Washington, DC 20503, Telephone (202) 395-6803.
Leon Panetta
Director